Capacity
Productivity
Safety

How to speed up production and make it more efficient

  • Sector
    Aeronautics
  • Size of entity
    Site with 500+ people, 150-person perimeter
  • Challenges of the mission
    Get everyone involved to work together: production, logistics, design, technical preparation, etc.

Client context

The need was to reduce the Production Interval (PI) from 19 days to 10 days, in a context of increasing customer demand with new export sales. 

Initial findings revealed the following loss-making factors:

  • Time wasted in finding the right parts (delivery of large crates of different parts to the edge of the line).
  • Journeymen would go to the logistics store themselves to replenish their supplies of hardware and cutting tools, or when a part was missing.
  • Workers changed shifts and products in progress remained stationary, as production was organized in Docks.
  • Ergonomics/safety: risk of falling, high-rise workstations not secured.

Support put into place

  • Line up the workshop. This was done in conjunction with the journeymen: we took all the instruction sheets that had been annotated by the journeymen for years, and created a product sheet. This enabled us to build a line balancing system together, and to determine the tools, parts and resources required for each workstation.
  • Creation of new frames to improve work ergonomics and ensure safety (working on the ground as much as possible, and installation of a secure footbridge when working at height).
  • Implementation of Lean logistics: supermarket and small train: 2x delivery per shift to bring the necessary parts kits to the line edge: control of the backlog.
  • Introduction of a new human resources organization: performance and contingency management, introduction of reference journeymen, integration of control into the UAP, etc.
  • Length of the mission
    20 months
  • GEOLEAN Team (FTE)
    4 persons
  • P&L earnings
    2,2 M€ annually

Results

  • Capacity: installation of a line taking out a complete section and checked every 10 days
  • Productivity: 46% reduction in hours clocked per section
  • WIP: reduction from 9 (at PI 19) to 6 (at PI 10), i.e. 52%.
  • Cycle time: reduction from 179 days to 82 days, i.e. a 52% reduction

What our clients say

« At first, I was afraid of what we were going to do with the project, but now I understand better and your approach is really great »

Nicolas - Line journeyman

« This has enabled us to put everything back on track, it was a hell of a job »

Lucien - Technical preparer (Industrialization)

« The objectives were ambitious, and we've done a remarkable job. We're now tackling the second section following on from the first »

Pascale - APU Lead

« This project is a major success for the site, and the group »

Fabrice - Plant Manager
Want to know more?
Contact